Weekly Lane and Ramp Closures

Night Closures: Monday, July 28, 2014

Lane Closures:
WestboundFULL Freeway closures from 8:00 p.m. to 5:00 a.m.

  • All lanes from the Vineyard off-ramp to the Halona St on-ramp will be closed.
  • Eastbound-  PARTIAL Freeway closures from 8:00 p.m. to 5:00 a.m.

  • Three right lanes from the Likelike off-ramp to the Queen Emma overpass will be closed.  The left lane nearest the median will be open to motorists.
    Ramp Closures:
    Westbound- The Punchbowl, School St and Likelike on ramps, and the Houghtailing  off-ramp will be closed.  At 10:30:pm the Middle St exit will close.  The Halona St on-ramp will be open.
    Eastbound- The Kalihi St on-ramps (both mauka and makai) will be closed.  All other on and off ramps will be open.
     
    Detailed Schedule: 

    Monday, July 28 – Tuesday, July 29

    During this phase of the project, work at night will incur full and partial freeway lane and ramp closures in both directions from 8:00 p.m. to 5:00 a.m. from Likelike Highway to Ward Avenue at 8:00 p.m., re-opening by 5:00 a.m.

    The public is encouraged to use alternate routes or to avoid the area if possible.

    Detailed Schedule:

    Monday, July 28

    DAYTIME: No work

    NIGHT: *** FULL FREEWAY CLOSURES from 8:00 p.m. – 5:00 a.m. ***

    Eastbound – Palama Separation bridge joint repair

    Westbound – Final striping & eradication, electrical work, install destination and regulatory signs, reconstruction near Punchbowl St on-ramp

    Tuesday, July 29

    DAYTIME:

    Eastbound – No work

    Westbound – Electrical/lighting work

    NIGHT: *** FULL FREEWAY CLOSURES from 8:00 p.m. – 5:00 a.m. ***

    Eastbound – Kapalama Bridge joint repair

    Westbound –Final striping & eradication, electrical/lighting work, install destination and regulatory signs, reconstruction near Punchbowl St on-ramp

    Work Synopsis for next week:  Wednesday July 30 – Thursday July 31

    DAYTIME: No work

    NIGHT: *** FULL FREEWAY CLOSURES from 8:00 p.m. – 5:00 a.m.  ***

    Eastbound – Kapalama Bridge joint repair

    Westbound - Final striping & eradication, electrical/lighting work, install destination and regulatory signs, reconstruction near Punchbowl St on-ramp

    H1 Rehabilitation Hotline